Construction Materials And Technology: UNIT V: Construction Planning: Questions And Answers
TWO MARKS QUESTIONS AND ANSWERS
1. Define Construction planning.
Construction planning is a primary and demanding activity in the
construction management and execution of construction projects. It involves the
selection of technology, the definition of work tasks, the estimation of the
required resources and durations for individual tasks, and the identification
of any relations among the different work tasks.
2. What is the necessity for
construction planning?
Planning is essential to ensure proper utilization of human and
material resources to achieve the objectives of the project. Construction
project planning includes the estimate, budget, time schedule, sequences of
completion of each activity of the project, resource and manpower planning.
3.
Classify the different types of construction projects.
Depending on the nature of
the construction facility, major construction projects are classified as
follows:
❖ Building Projects
❖ Infrastructure Projects
❖Industrial Projects.
❖ Special-Purpose Projects
4.
What are the steps involved in the construction planning?
The following are the
steps to be followed in a construction planning:
❖ Project initiation
❖ Creating the project plan
❖ Executing the plan
❖ Tracking the project progress
❖ Evaluation of the project
5. What are the objectives of
construction planning?
The main objective of
planning is to execute the project most economically within the time schedule.
Effective planning includes the following factors:
❖ Each element of the project should be properly designed.
❖ Selecting proper equipment
and machinery accordingly to the nature of the project.
❖ Arranging proper maintenance facility for equipment and machinery
near the project site to avoid hindrance due to breakdown.
❖ Procuring materials well in advance and stocking at the site to
avoid delay due to insufficient storage.
6. State the Principles of
construction Planning.
The following are the
principles of construction planning:
❖ The plan should present
the information in an easily understandable manner, irrespective of the complex
situation in the project.
❖ The plan should be realistic, flexible and comprehensive.
❖ The plan should provide a
source for project monitoring and control process.
7.
List the types of construction project planning.
The following are some of the most common types of construction
project planning processes:
❖ Strategic
planning
❖ Operational planning
❖ Business planning
❖ Resource planning
8.
Define resource planning.
Resource planning ensures that each project a company is
currently working has sufficient staff, materials and resources necessary to be
completed successfully and on time. To keep everything organized, project managers
often create milestone dates and deadlines, as well as a list of where they
plan to allocate necessary resources. This can be beneficial if multiple
projects are in progress at the same time.
9.
What are the stages of Construction planning?
The various stages in the planning process are:
❖ Preplanning
❖ Detailed Planning
❖ Monitoring and Control
10. List the advantages of
Construction planning.
The following are the advantages of construction planning:
❖ The contractor can get a
clear scenario about the sequence of work, since the construction plan is
detailed through sketches, bar charts etc.
❖ It helps to maintain the
financial cash flow of the contractor through proper resource management.
❖ Labour requirement can also be managed properly through appropriate
planning for each activity.
❖ Various sub activities
of the project can also be identified and actual work can be measured easily by
the contractor.
❖ The client will know exactly how long it will take to complete
the project.
11. List the disadvantages of
construction Planning.
The following are the disadvantages of construction planning:
❖ The effectiveness of the plan depends upon the correctness of
assumptions.
❖ In certain big projects planning is expensive and might delays
action.
❖ Planning encourages a false sense of security.
12. Define Construction Scheduling.
Construction scheduling can be defined as the process of listing
all the activities to be carried out with the planned start and completion
dates. It is an entire blueprint which shows how the project will be executed
and the sequential relationship among the various activities or operations in a
project so that work roid can be carried out in an orderly and effective
manner.
13. What are the steps involved in
construction planning?
The steps involved in
construction scheduling are:
❖ The project is divided into number of operations and the
sequences of these operations can be derived after knowing their relationship
properly.
❖ The quantity of work involved in each operation has to be
calculated.
❖ The time required for completion of the project and different
activities are to be calculated.
14. List the various types of
construction schedule.
The various types of construction schedules can be listed as
follows:
❖ Construction Material Schedule
❖ Labor Schedule
❖ Equipment Schedule
❖ Financial Schedule
❖ Control Schedule
❖ Organization Schedule
❖ Summary Schedule
15. List the methods of construction
scheduling.
Construction scheduling can be done depending on the nature of
the project. The various methods of scheduling are discussed as follows:
❖ Gantt chart
❖ Q Scheduling
❖ Last Planner System
❖ Line of Balance
❖ Work breakdown structure
❖ Critical Path Method (CPM)
❖ Program Evaluation and Review Technique (PERT)
16.
Write about Gantt chart.
Henry Gantt (1861-1919), an American mechanical engineer,
designed the Gantt chart. Gantt chart is a common construction scheduling
method which utilizes the bar charts to depict the plan and the progress of the
project. The unique aspect of this scheduling technique is that it highlights
the dependency of one task or activity on the other to be completed efficiently
in the given time. These are also known as bar charts. A Gantt chart helps in
scheduling, managing, and monitoring specific tasks and resources in a project.
17. What do you mean by Quantitative
scheduling?
Quantitative scheduling, also known as Q scheduling, uses bar
charts to visualize resource quantities and the locations in which the
resources will be used. It is a different type of construction scheduling
method. It focuses on scheduling the materials and equipment used in the
project. It provides a clear description of the materials used and required in
the project through a bar chart.
18. How can you explain LOB?
Line of balance (LOB) is a scheduling method which is usually
implied in projects that include repetitive activity. The balance scheduling
method measures the cost, time, and project completion plan and ensures nothing
falls behind the schedule. These type of schedules are very uncommon but are
sometimes used when a construction project consists of highly repeatable and
similar tasks. These are most commonly used for roadways, pipes, and other
horizontal construction projects.
19.
What are the procedures to be followed in LOB?
For preparing a line of balance schedule, the following
procedures should be adopted:
❖ Prepare a logic diagram.
❖ Estimate the man-hours
required to complete each operation.
❖ Choose buffer times which will guard against the risk of
interface between operations.
❖ Calculate the required
output target in order to meet a given project completion date.
❖ Complete the LOB schedule.
❖ Examine the schedule and assess possible alternatives to bring
about a more 'balanced' schedule.
20.
Write short notes on WBS.
The Work breakdown structure (WBS) is the tool that is used to
record and communicate the project deliverables and sub-deliverables as well as
the accomplishments and sub-accomplishments. WBS is a visual, hierarchical and
deliverable-oriented deconstruction of a project. It is a helpful diagram for
project managers because it allows them to break down their project scope and
visualize all the tasks required to complete their projects.
21. List the advantages of
deliverable WBS.
The advantages of a deliverable-oriented WBS are: do It
simplifies the process of cost estimating.
❖ It allows us to see the total work scope.
❖ It clarifies the relationships among elements.
❖ It can be used during all project phases.
❖ It's easier to modify as the project changes.
❖ It supports earned value management.
22. What do you mean by CPM?
The critical path method is one of the most common construction
scheduling methods, and it is also called a critical path analysis. This type
of schedule is developed by creating a network diagram highlighting the
sequence of tasks and projects following the specific path. The CPM creates a
schedule based on critical activities, which must be completed before another
activity can begin. Once critical activities are identified, they are scheduled
in sequence to determine the least amount of time a construction project can be
completed.
23. Write short notes on PERT.
The program evaluation and review technique (PERT) is one of the
most critical construction scheduling methods. This is because it pays more
attention to analyze all the individual project activities. In other words,
PERT evaluates and reviews the project's activities in progress and evaluates
the time duration in which they will be completed.
24. What is a critical activity?
The activities with zero total float are known as critical
activities. In other words an activity is said to be critical if a delay in its
start will cause a further delay in the completion date of the entire project.
25. Write about optimistic and
pessimistic time.
❖ Optimistic Time (to): It is the shortest
possible time in which the activity can be finished. It assumes that everything
goes very well. This is denoted by to.
❖ Pessimistic Time (t):
It represents the longest time the activity could take if everything goes
wrong. As in optimistic estimate, this value may be such that only one in
hundred or one in twenty will take time longer than this value. This is denoted
by tp.
26. How will you calculate expected
time?
Expected time is the average time an activity will take if it
were to be repeated on large number of times and is based on the assumption
that the activity time follows Beta distribution, this is given by
te = (to +4 tm + tp)/6
Construction Materials And Technology: UNIT V: Construction Planning : Tag: : Construction Planning | Construction Materials and Technology - Two Marks Questions and Answers